10 May Construction update starting week of May 13, 2024
The Rebuild Downtown construction project is going well.
Current Work Week (May 13, 2024)
- Demolition along 18th St.
- Demolition along 2nd Ave.
- Water main installation
2 Week Look Ahead (May 20, 2024)
- Water main installation and testing
Traffic Control
- 18th St. from 1st Ave. to 3rd Ave. is closed, including the intersection of 18th St. and 3rd Ave.
- 3rd Ave. from 18th St. to the WHBF tower will be closed