The  Rebuild Downtown construction project continues to move forward. Current Work Week (May 27, 2024) Water main installation 2 Week Look Ahead (June 3, 2024) Water main installation IMPORTANT UPDATES   Water/Sewer Connections Building owners in the project area have a timely and...

The Rebuild Downtown construction project is going well. Current Work Week (May 13, 2024) Demolition along 18th St. Demolition along 2nd Ave. Water main installation 2 Week Look Ahead (May 20, 2024) Water main installation and testing Traffic Control 18th St. from 1st...